August 2018

Outage works have been in progress in August. Since production equipment in the plant is very varied, the outage does not influence supplies to customers. Scheduled maintenance was performed on coal boilers, FGD unit and the steam turbine. Gas engines are to be maintained during the second half of the month. At the end of the month the whole plant will be ready for the next winter.

Beside scheduled and emergency maintenance, the plant staff is busy working on development projects - heat distribution pipeline to Planá nad Lužnicí is being built and the project of photovoltaic power plant with accumulation and the project of extension of the local electricity distribution system have been under preparation. 